68. Background jobs get a soft deadline before the hard timeout

Date: 2026-10-19

Status: Accepted

Context

A spawn_background_agent job runs under a hard execution timeout (Manager.jobTimeout, default 20 minutes, background_agent_timeout_minutes). At the deadline the context is cancelled and the job fails with timed out after 20m0s. Issue #271 documents a live case: a research job on mimo-v2.6-flash ran the full 20 minutes (25 requests, ~90 s TTFT) exploring three targets, never wrote up, and returned only the noFinalSummaryTrailHeader trail — tool names and 200-character result heads, none of the findings the model had formed.

Two properties make this a milk problem rather than only model behavior:

  • The model is never told it has a time budget, so nothing prompts a wrap-up before the cut.
  • The timeout was already raised once (10 → 20 minutes, background-subagents-implementation-plan.md item 12) for the same symptom. A bigger number only moves the cliff; loop detection, not the timeout, is the defense against stuck jobs, so the timeout's remaining role is to stop a job that is working but will not finish — and that job should still hand back what it has.

Decision

  1. Soft deadline. At 80% of the job's timeout, Manager sends a wrap-up message through the job's existing inbox (Manager.Send, the send_background_agent path, delivered as a user message at the next tool-loop iteration): the minutes remaining, an instruction to stop exploring and write the final answer from what it has, and the <result status="partial" …/> convention if incomplete. Sent once per job. Delivery is best-effort, as for any inbox message.
  2. Hard cancel unchanged. The execution deadline stays the backstop; nothing is extended.
  3. Salvage on hard timeout. A job that still times out records its last non-empty assistant text alongside the tool trail in Job.Result, so the findings it had formed are not lost.
  4. No new config. The fraction is a constant (80%) and follows background_agent_timeout_minutes. Jobs with a timeout under 2 minutes skip the soft deadline.

Consequences

  • Most would-be timeouts turn into a partial result the spawning agent can use, instead of a failure.
  • A model that ignores the message still times out exactly as before — no regression, just the salvage improvement.
  • The wrap-up message costs one extra user message in the job's context, only for jobs that run past 80% of the timeout.
  • Workflow stages and foreground turns are unaffected; this applies to Manager jobs only.

Implementation: Manager.Spawn / finish in internal/agent/local/background.go; plan in docs/internal/plans/background-job-soft-deadline-plan.md.